Potable Water Projects

Explore Our Potable Water Projects

Wayne Haefele & Associates, Inc., situated in Lopez Island, Washington, takes pride in providing the San Juan Islands with cutting-edge potable water solutions. We have more than 30 years of experience and have successfully finished a range of potable water projects that improved the dependability and quality of water for both public and private customers. View our project gallery to see how our construction and design experience has contributed to these communities.

 

Are you ready to begin your next project? Call (360) 472-1407 to arrange an estimate now!

Water Treatment Plant GAC Adsorption Project

A large blue building with a fence around it and trees in the background

Building framed around the tanks

A large building is being built with a genie lift in front of it.

Building nears completion

A white building with a yellow fire hydrant in front of it.

The completed project

Building framed around the tanks

Building nears completion

Wayne Haefele & Associates, Inc. provided construction inspection and management for the Town of Friday Harbor’s project, which addressed issues with trihalomethanes (THMs) and seasonal taste and odor complaints. The Town uses surface water from a watershed and reservoir, which is treated at a filtration facility and then piped to the water department. Due to increasingly strict THM regulations, the Town faced challenges meeting the limits. After exploring alternatives, they chose to add granular activated carbon (GAC) adsorption.

 

The project involved installing a Calgon Model 10 GAC system in a pre-engineered metal building, along with the necessary piping, valves, and civil work. Wayne Haefele & Associates, Inc. provided construction oversight, developed disinfection and dichlorination protocols, and supported plant operators during start-up. The project was completed on time, under budget at $568,170.75, and exceeded water quality goals.

Rancho Monte Alegre Project

A group of men are working on a water pipe in a trench.

Transmission main and lateral in one trench

A construction site with scaffolding and a truck in the background on a foggy day.

Tank under construction

A small house with a wooden gate in front of it and mountains in the background.

Electrical - HOCL building

A few small rocks in the alignment

New tank floor poured

Seismic cables

Whiffle tree for setting reinforcing mats

Interior piping in construction

Transmission main and lateral in one trench

Tank under construction

The Rancho Monte Alegre Project for Carpinteria Water District, Carpinteria, CA

Wayne Haefele & Associates, Inc. provided design, construction management, and inspection services for the Rancho Monte Alegre Project, which aimed to give the Carpinteria Valley Water District greater autonomy from the South Coast Conduit. The project included a 3.8 MG concrete storage tank, a blending station, a pump station, a 20” transmission main, and water and sewer laterals. A key challenge was managing community opposition, particularly from affluent neighbors, and navigating complex site conditions with rocky terrain and protected species.

 

The project was designed in two bid packages. Bid Package #1 involved constructing a paved roadway, installing a 20” PVC” transmission main, and extending 12 distribution mains.

 

Bid Package #2 focused on the tank and supporting infrastructure on a steep, 21-acre site, including pumps and utility building. Challenges included rock excavation, stormwater management, and integrating design plans with a private developer’s plans.

 

Wayne Haefele & Associates, Inc. was involved in hydraulic analysis, materials evaluation, design documentation, and providing ongoing construction management. We ensured compliance with permit conditions, coordinated inspections, and addressed technical issues, completing the project with the successful integration of all systems.

Share by: